Welcome Visitors
Five Island Lake
Restoration Accomplishments
"Five Island Lake is an excellent choice
for a dredging project for three reasons: 1) an extremely low sedimentation
rate; 2) public participation; and 3) low cost" according
to Roger Bachmann, a world renowned limnologist at Iowa State University.
Five Island Lake restoration project has unique features that separates it from all other lake restoration
endeavors. First is the community support in donation
of time and money. The initial bond issue of $400,000 passed by 90% in
a community of 4,500 inhabitants. The total contribution of the community
to date exceeds $1,200,000.
Second, the dredging aspect of our program
is the largest ever of a natural lake in the United States. In the lower
600 acres of this lake, the water level will be deepened from its former
4 to 6 feet to 14 to 16 feet with several areas dredged to over 20 feet.
When finished, at least 4,500,000 cubic yards of silt will have been
removed. Size was not the original objective, but because of the extensive
dredging, this project will serve as a laboratory to determine what can
be accomplished by the large scale removal of silt. Our water monitoring
data to date demonstrates in Area 5 where 85% of the silt has been removed
compared to Area 1 which has not been dredged, a lessening of suspended
solids, total phosphorus, and chlorophyll "a" and an increased
measurement in the Secchi disk depth--all indications of improved water
quality.
Third, our costs are much lower than
similar endeavors by the government. We believe our costs will be approximately
50 cents a cubic yard of silt removed. Most government dredging operations
are at least $2.00 a cubic yard. We are able to do this because we own
our own dredge and hire our own employees. Although we have an experienced
project manager, many of the tasks that government would pay for are donated
by Lake Board members and other citizens. For example, legal work is extensive
because of numerous contracts for silt deposit sites, but legal fees have
been minimal.
Fourth, we have the oldest volunteer
lake monitoring program in Iowa. Our main goal is improved water quality.
To check our progress we have been collecting water samples as stated
above since 1991. The chemical analysis is performed at the Civil Engineering
Laboratory at Iowa State University using EPA approved methods. We expect
to continue this program for at least three years after dredging ceases.
Lastly, the duration of benefits will
last for hundreds of years. In 1993, Iowa State University studied Five
Island Lake and our project. The year 1993 was noted for the large amount
of rainfall, but even during that year Iowa State's measurement of silt
running back into the lake was 0.2 inches per year, one of the lowest
siltation rates of any lake in Iowa. Since we are lowering the silt bed
by 10 1/2 feet or 126 inches, calculations indicate our efforts will last
for at least 600 years.
Results
Below are two diagrams that succinctly illustrate the
extent of the siltation problem in Five Island Lake when this project
began. Below it is a second diagram which illustrates what we have accomplished
to date. These are not cross-sectional diagrams of the lake but are water
levels and silt levels from south to north the five-mile length of the
lake.
Five Island Lake Before Restoration. This map demonstrates the predominance of silt volume over water volume
in the Five Island Lake bed. This drawing was made in 1935 but the same
conditions were present in 1989 when the present project began. Water
this shallow is useless for recreational purposes.

Five Island Lake As It Exists Now. The
removal of silt by hydraulic dredging, accompanied by shoreline stabilization
and watershed management has removed 5,000,000 cubic yards of silt and
replaced this with water. Water clarity has markedly improved.

|